On September 13, 2011, a 38 year-old miner with 3 years of experience was killed at a portable sand and gravel operation. The victim opened the 480 volt feeder box at the motor control center and started to remove the leads when he received a fatal shock.
- Be trained on all the electrical tests and safety equipment necessary to safely test and ground the circuit being worked on.
- Conduct a risk assessment.
- Use properly rated Personal Protective Equipment (PPE) including Arc Flash Protection such as a hood, gloves, shirt, and pants.
- Positively identify the circuit on which work is to be conducted.
- De-energize power and ensure that the circuit is visibly open.
- Place YOUR lock and tag on the disconnecting device.
- Verify the circuit is de-energized by testing for voltage using properly rated test equipment.
- Ensure ALL electrical components in the enclosure are de-energized.
- Ground ALL phase conductors to the equipment grounding medium with grounding equipment that is properly rated.